Installation Guide: Asset Gateway

    Audience Drivers
    Applies To Asset Gateway

     

    Introduction

    The Motive Asset Gateway provides next-generation GPS tracking for trailers, equipment, and other assets. It is designed to help fleets understand the location of their assets, maximize utilization, prevent unauthorized use, and simplify dispatching to save time and money across fleet operations.

    Installation of an Asset Gateway differs between trailer type and power source. This article will cover the various aspects to look for when installing your Asset Gateway.

     

     

    Installation Requirements 

    Check the following things if you plan to utilize solar power:

    • Asset Gateway's solar panel has a clear line of sight to the sun.
    • When selecting a location for installation, make sure the placement should not interfere with the safe operation of the vehicle and cause damage to the Asset Gateway.
    • Peel the sticker on the solar panel and check if the LED on the Asset Gateway unit lights up green.

    asset_gateway.jpg

     

    Note: It’s important that the LED turn up green to start the Asset Gateway Installation process. If there is no sign of LED activity, click here.

     

    What comes in the box?

    • Asset Gateway
    • Mount Plate
    • Four M3 Screws
    • Power cable

    In this article you’ll learn:

    • Mount Plate Installation
    • Installing Asset Gateway to Dry Vans
    • Installing Asset Gateway to Reefers
    • Installing Asset Gateway to Flatbeds
    • Installing Asset Gateway to Tankers

    Steps : Installing Asset Gateway

    Mount Plate Installation

    Note: Place the mount plate for the Asset Gateway on the outer walls of the trailer to avoid GPS problems. Placing the Asset Gateway on the inner walls can be a hindrance to good GPS signals causing issues in tracking.

    • Use the M3 Screws to attach the Asset Gateway to the mount.

    asset_gateway1.jpg

     

    Installing Asset Gateway to Dry Vans

    • Attach the Asset Gateway to the Mount Plate using the four M3 screws provided.
    • Install the Mount Plate with the attached Asset Gateway near the top of the front bulkhead (the side closest to the tractor) using the four self-tapping screws (with washers).
    • Make sure the solar panel has an unobstructed view of the sky.

    asset_gateway2.jpg

     

    Installing Asset Gateway to Reefers

    It is necessary to connect the Asset Gateway via the power cable to the refrigerated trailer unit. Once the unit is cable powered, it could be installed on top of the refrigeration unit.

     

    Note: Learn more about how to connect the Asset Gateway using the power cable by clicking here.

     

    asset_gateway3.jpg

     

    Installing Asset Gateway to Flatbeds

    • Attach the Asset Gateway to the Mount Plate using the four M3 screws provided.
    • Install the Mount Plate with the attached Asset Gateway near the top of the front bulkhead (the side closest to the tractor) using the four self-tapping screws (with washers).
    • Make sure the solar panel has an unobstructed view of the sky.

    asset_gateway4.jpg

     

    Installing Asset Gateway to Tankers

    • Identify a mounting spot on the top of the tanker along the walkway or roll bar that is away from any loading or unloading areas.
    • Install the Asset Gateway using the four self-tapping screws (with washers).
    • You may use the Mount Plate to position the Asset Gateway so it has an unobstructed view of the sky.

    asset_gateway5.jpg

     

    Additional Notes

    Below are three incorrect installations:

    • Solar-powered unit installed without a solar mount.
    • Solar peel sticker was not removed.
    • The unit was installed on a curved surface and not a flat surface.

     

    Related Content

    Was this article helpful?
    9 out of 11 found this helpful

    Share this with others